Skip to main content
QuoteMyPower 26 Indian makers · 16 cities
Car charging station on the IIT Kanpur campus

Mumbai, Maharashtra — distribution by Adani Electricity, BEST and Tata Power.

Setting up an EV charging station in Mumbai

₹9.5–13.5
Commercial tariff you pay, per unit
₹20–26
What public DC charging retails at locally
1,350
Solar units per kW per year here

Photo by Dr Vinamra, CC BY-SA 4.0

A 60 kW dual-gun DC station in Mumbai costs roughly ₹9 to 19 lakh all-in. Your local distribution utility is Adani Electricity, BEST and Tata Power (by area), commercial power runs ₹9.5–13.5 per unit, and public DC charging retails locally at around ₹20–26 per unit.

Mumbai has the strongest four-wheeler EV demand in India but also the highest site costs and the worst parking economics. Mall and office basements with existing sanctioned load are the realistic opportunity, not new standalone stations.

We collect your requirement once, verify it on a call, and send the identical brief to vendors who actually work in Mumbai — so the quotes you get back are comparable on landed cost rather than on hardware price.

The local numbers that decide your project

National averages are useless when you are deciding on one site. These are the figures that actually move your payback in Mumbai.

Distribution utility
Adani Electricity, BEST and Tata Power (by area)
Commercial tariff per unit
₹9.5–13.5
Public DC charging retail rate
₹20–26
Solar yield, if you add an array
1350 units/kW/yr
Areas with the strongest demand
Andheri · BKC · Powai · Thane · Navi Mumbai · Lower Parel
Highway and arterial corridors
Mumbai–Pune Expressway · Western Express Highway · Eastern Express Highway

Getting your connection from Adani Electricity, BEST and Tata Power (by area)

Mumbai is split between three distributors and which one serves your building changes both your tariff and your connection process. This is the single biggest source of confusion in Mumbai quotes.

Whatever your utility, the sequence is the same: check your existing sanctioned load from your latest bill, apply for a commercial connection at the load your charger needs on top of that, and find out early whether the local feeder or distribution transformer can carry it. Where it cannot, you pay for the upgrade — and that is the line item that turns a ₹10 lakh project into a ₹15 lakh one.

What the full cost looks like

The charger is the number every vendor shows you. The other four lines are where first-time buyers in Mumbai lose ₹2–5 lakh they had not planned for.

What a 60 kW DC station costs you beyond the equipment, India, 2026
What you are paying for Low High Why it moves
Civil work, canopy, foundation, cabling ₹1.5 L ₹3.0 L Higher if you want weather protection and lighting, which you should.
Transformer or sanctioned load upgrade ₹1.0 L ₹4.0 L The single most common budget shock. Depends entirely on your existing feeder.
DISCOM commercial connection, deposits, liaisoning ₹0.50 L ₹2.0 L Security deposit scales with sanctioned load and is refundable but ties up cash.
Network software, signage, commissioning, first-year AMC ₹0.40 L ₹1.5 L Platform commission on every unit sold is separate and ongoing.
Site works, before equipment ₹3.4 L ₹10.5 L Add the manufacturer's equipment quote to this. Compare the total, never the hardware alone.

Model a station in Mumbai

Set your electricity cost to the ₹9.5–13.5 band and your selling price within the ₹20–26 local range, then be honest about cars per day.

6
25 kWh
₹20/kWh
₹8/kWh
Monthly margin after all running costs
—
Payback
—
Capacity actually used
—

Indicative only, and deliberately includes the costs vendor calculators leave out. It excludes rent, staff, GST treatment and your DISCOM's specific demand-charge structure.

Also worth doing in Mumbai

Solar yields 1350 units per kW here

Commercial tariffs are among the highest in India, which means solar payback is fast — but usable roof area per unit of load is the constraint. Societies and low-rise commercial do better than high-rises.

Since a charging station's main cost is the electricity it buys, and both projects need the same site survey and load study, Mumbai sites frequently do better installing both at once than a year apart.

Where charging demand is in Mumbai

  • Andheri
  • BKC
  • Powai
  • Thane
  • Navi Mumbai
  • Lower Parel

Corridors

  • Mumbai–Pune Expressway
  • Western Express Highway
  • Eastern Express Highway

EV charging questions, answered for Mumbai

How much does an EV charging station cost in Mumbai?

A 60 kW dual-gun DC station in Mumbai costs roughly ₹9–19 lakh all-in — ₹6–10 lakh for the charger and the rest for civil work, a transformer or sanctioned-load upgrade, and the commercial connection from Adani Electricity, BEST and Tata Power (by area). Your position on that range depends almost entirely on whether your site's existing feeder can carry the extra load.

Which electricity board handles EV charging connections in Mumbai?

Adani Electricity, BEST and Tata Power (by area). Mumbai is split between three distributors and which one serves your building changes both your tariff and your connection process. This is the single biggest source of confusion in Mumbai quotes.

What is the commercial electricity tariff in Mumbai?

Commercial consumers in Mumbai typically pay ₹9.5–13.5 per unit, and public DC fast charging retails locally at around ₹20–26 per unit. That spread is your gross margin before demand charges and platform commission. Confirm your own slab from your latest bill, since tariffs vary by consumer category and sanctioned load.

Is Mumbai a good location for a charging station?

Mumbai has the strongest four-wheeler EV demand in India but also the highest site costs and the worst parking economics. Mall and office basements with existing sanctioned load are the realistic opportunity, not new standalone stations.

Do I need a licence to open an EV charging station in India?

No licence is required. The Ministry of Power has explicitly de-licensed EV charging — operating a public charging station is not a regulated activity, so you do not need a power trading or distribution licence. You do need a commercial electricity connection from your DISCOM with adequate sanctioned load, and your installation must meet CEA safety standards and local electrical inspectorate approval. GST registration applies to the service revenue.

How long does it take to get an EV charging station running?

Six to twelve weeks if your electrical infrastructure is already adequate, and three to six months if it is not. The charger itself arrives in two to four weeks. What sets your timeline is the DISCOM: a commercial connection on an existing adequate feeder can be sanctioned in three to four weeks, while a transformer upgrade or new feeder can take three months or more depending on your utility.

Get Mumbai quotes

Vendors who actually serve Mumbai, quoting against the same brief. Free for buyers, and we will tell you if your site does not work.

Call +91 77788 04214 or message us on WhatsApp.

Nearby: Pune , Nashik

Ask on WhatsApp